Ethiopia vcd bestbetplanning

From livestock-fish ilriwikis

Targeting Action Research on Small Ruminant Value Chains in EthiopiaThree Multi-stakeholder workshops Lowland sheep and goats, 1-2 April 2013, Debre Zeit Abergelle goats and Atsbi sheep, 19-20 March 2013, Mekelle Highland sheep, 14-15 March 2013, Addis Ababa


Stakeholder discussions and planning for the Livestock and Fish small ruminant value chain development project began in mid 2012. By November, sites were selected and [http:livestockfish.cgiar.org/2012/11/05/ethiopia-value-chain-sites-selected-rapid-value-chain-assessment-initiated/| teams were trained] to carry out rapid value chain assessments in the project's 7 research sites (including for the [http:safefoodfairfood.wordpress.com/2012/11/29/icarda-ilri-training-on-tools-for-rapid-assessment-of-sheep-and-goat-value-chains-in-ethiopia/| safe food fair food] project).

In March and April 2013, three workshops were organized to take stock of the value chain assessments and formulate 'best best' intervention plans for each of the sites. The objectives of each workshop wre:

  1. Share and validate results from the rapid VC assessment in the 8 sites
  2. Draft a vision/outcome statement for each VC site
  3. Identify and prioritize best bet interventions for each site
  4. Develop intervention plans for each site (to be taken later to local VCD actors and communities)
  5. Identify emerging cross-cutting issues by research components – breeding, feeding, health, gender.

Outputs from workshops are below the agenda

See photos

See News item

Short report

Participants

File:et_vca_bestbets_people.xlsx


Draft Agenda

DAY 1
0845 - 0915 Welcome, objectives
Introductions
The Livestock and Fish Program in Ethiopia
Facilitator

Barbara
0915 - 1000 VC assessment reports - brief presentations Presentations
1000 - 1030 Break
1030 - 1230 Validating the site assessments - constraints, opportunities, interventions Facilitator
Group work
1230 - 1400 Break
1400 - 1500 Value Chain vision development, per site [brainstorm]
- for each chain, what the desired/expected results in 5/10 years?
Facilitator
Group work
1500 - 1515 Break
1515 - 1715 Identify potential 'best bet' research and development intervention strategies per site.
- Needs, opportunities, gaps, feasibility
- Researchable issues
- immediate, medium and longer term time horizons
- expected results

Produce 'pitch' for the next morning
Facilitator
Group work
DAY 2
0845 - 1000 Presentation site intervention strategies
- 2 tough questioners
- plenary Q&A
Presentations
1000 - 1030 Break
1030 - 1130 Quick cross-validation by 'component': breeding, feeding, genetics, gender, ... Facilitator
Group work
1130 - 1300 Formulate research and development intervention plans per site
- who [delivery team]
- when [timelines]
- how [plans per priority intervention]
Facilitator
Group work
1300 - 1400 Break
1400 - 1600 Research and development intervention plans per site
- finalization of plans
- presentation of plans
- critique of plans
Group work

Presentations
1600 - 1615 Next steps
Close


Addis Ababa workshop

Presentations:

Products: File:horro_plan_v1.doc

File:menz_bestbets_v1.pptx

File:doyogena_bestbets_v1.pptx


Mekelle workshop

Presentations:


Products:

File:waq_abergelle_plan_v1.docx

File:atsbi_plan_v1.docx

File:tanqua_abergelle_plan_v1.docx


Debre Zeit workshop

Presentations:


Products:

File:borana_plan_v1.docx

File:shinelle_plan_v1.docx